Navigating Septic System Timelines
Nov
15

Navigating Septic System Timelines for Your New Sposen Home

Building your dream home is an exciting journey, and at Sposen Homes, we’re committed to keeping you informed every step of the way. One critical aspect of the construction process that often requires extra attention is the septic system permit, installation, and inspection process. As we collaborate with the health department to secure necessary permits and complete inspections, we want to ensure that you have a clear understanding of the current timeline expectations for these processes. 

Understanding the Septic System Process 

For new home construction, the septic system installation requires several specific steps, which must be completed in partnership with the health department. Here’s a breakdown of the process and the current estimated timelines. 

  1. Initial Permitting Steps:
  • Septic System Permit: Before we can submit your home building permit, it’s necessary to secure a septic permit from the health department. 
  • Current Processing Time: 8-10 weeks. 
  • Corrections and Resubmissions: If any part of the permit application requires clarification or correction, we will address these promptly. 
  • Resubmission Processing: 1-3 weeks, depending on the corrections’ complexity. 
  1. During Construction:
  • Inspections and Compliance: Throughout the build, various inspections are required to ensure the septic system meets all codes. After our service provider conducts the inspection, the health department reviews the results. 
  • Current Review Time: 4-5 weeks from the inspection request date. 
  • Correction Timelines: Should any corrections be necessary after an inspection, these typically take 1-3 weeks to complete. 
  1. Final Steps to Completion:
  • Once the health department approves the final inspections, the documents are forwarded to the building department. This final step can vary slightly depending on the municipality. 
  • Final Review Timeline: 24 hours to 5 days for closed-out septic permit notification. 
Staying Updated 

While we strive to keep everything on schedule, these timelines can fluctuate due to the health department’s workload. Sposen Signature Homes is dedicated to maintaining continuous contact with the department to track progress. Should any changes occur, we will provide updates through daily logs in Buildertrend. 

What This Means for You 

Understanding these steps and timelines can help you prepare for the construction phases that may require more time. At Sposen Signature Homes, we prioritize transparency, so you always know what to expect. By being aware of the septic system installation requirements and current processing times, you can feel confident that your new home is progressing with all necessary care and attention. 

For more insights on the construction process and tips on homeownership, stay connected with our blog. We’re here to help you navigate every aspect of building your dream home.  

Please note that these timelines are current as of October 1, 2024, and may be subject to change.